ENGINEERED IN NAIROBI. WORKING ACROSS EAST AFRICA.

Motor controls & automation

Compare starting methods around the machine, supply and operating sequence. Plan control, protection and commissioning together.

Start with your operating requirements.

Describe what the machine does at start-up, during normal operation and when it stops. Include any interlocks and the process response to a power interruption.

Request an application review ↗

Explore the equipment options.

Use these families to frame the system, then confirm the exact model and compatibility with an engineer.

Technical details and selection tools

Plan the next decision.

01 / Understand the duty

Start with the operating picture.

Describe what the machine does at start-up, during normal operation and when it stops. Include any interlocks and the process response to a power interruption.

02 / Check the interfaces

Gather the evidence.

Bring the motor nameplate, driven-load details and existing control drawings. Review starting method, overload protection and the required speed range as one system.

03 / Agree the output

Define the review you need.

Agree the operating sequence, control interfaces, test procedure and operator handover before the panel is built.

Work through a sizing scenario.

Choose a tool, replace the example inputs with site values, then save a scenario before changing your assumptions. Compare the results and include them in your project brief.

Enable JavaScript for interactive estimates or ask our engineering team.

Start with the application.

Fixed speed, simple sequence

Review DOL or star-delta starting against supply limits and machine acceleration.

Controlled acceleration

A soft starter may suit a fixed-speed duty; starting torque and thermal limits still matter.

Variable process demand

A VFD can control speed. Review motor compatibility, harmonics, cooling and cable length.

Can any motor use star-delta starting?

No. It needs a suitable three-phase motor, accessible winding terminals and a voltage rating compatible with delta operation on the supply. Verify the nameplate and load torque.

← Explore all application hubs

Specify the whole working system.

Start with the equipment duty. Add the control, protection and measurement functions that your project needs; these are options to review, not a pre-approved assembly.

Explore all 36 component families ↗

Understand the estimate.

These examples use the default inputs. Change the live controls above for your own scenario; the reference examples below remain fixed.

Motor starting current — worked example

Example inputs

  • Motor rating: 55 kW
  • System voltage: 415 V — industrial
  • Phase: 3Φ (three phase)
  • Starting method: Direct on line (DOL)
  • Efficiency: 92 %
  • Power factor: 0.86

Example result

  • Full load current: 96.7 A
  • Starting current: 580 A
  • Starting multiplier assumption: 6 × FLC

Assumptions & limits

  • Starting multipliers are illustrative, not measured inrush or guaranteed torque.
  • Verify motor nameplate, load acceleration, supply limits and starts per hour.
  • Preliminary planning only. Final selection needs project-specific engineering verification.
Motor energy comparison — worked example

Annual kWh = rated shaft kW × load fraction × annual hours / efficiency fraction. Cost difference uses the entered energy tariff.

Example inputs

  • Rated shaft power: 30 kW
  • Shaft load: 75 %
  • Existing efficiency at duty: 88 %
  • Replacement efficiency at duty: 93 %
  • Annual running hours: 4000 h
  • Energy tariff assumption: 25 KES/kWh
  • Installed replacement cost: 150000 KES

Example result

  • Existing annual energy: 102,272.7 kWh
  • Replacement annual energy: 96,774.2 kWh
  • Annual cost difference: 137,463 KES

Assumptions & limits

  • Both motors deliver the same shaft duty. Use efficiency at this load, not an unrelated nameplate point.
  • Tariff is your scenario input, not a published utility rate.
  • Simple payback excludes finance, maintenance, downtime and tariff changes. Negative difference means higher operating cost.
  • Preliminary planning only. Final selection needs project-specific engineering verification.

Technical reference: US Department of Energy: motor systems guide. This reference does not certify the website calculation or an NPE assembly.

MCB / MCCB / ACB sizing — worked example

Example inputs

  • Load value: 160
  • Unit: Amps
  • System phase: 3Φ (three phase)
  • System voltage: 415 V — industrial
  • Load profile: General power
  • Fault level: 25 kA
  • Altitude: 1700 m
  • Ambient temperature: 35 °C

Example result

  • Nominal rating (In): 200 A
  • Device frame: MCCB (moulded case)
  • Tripping curve: Curve C (5–10× In)

Assumptions & limits

  • Altitude derate: 0 % at 1700 m
  • Temperature derate: 4 % at 35 °C
  • Load profile factor applied: 1.1×
  • Preliminary planning only. Final selection needs project-specific engineering verification.

Understand the estimate.

These examples use the default inputs. Change the live controls above for your own scenario; the reference examples below remain fixed.

DC control power budget — worked example

Example inputs

  • DC output voltage: 24 V DC
  • PLC and other continuous load: 25 W
  • Simultaneously held DC coils: 6
  • Holding power per DC coil: 3 W
  • Simultaneous sensors: 10
  • Power per sensor: 0.5 W
  • Reserve allowance: 25 %

Example result

  • Connected continuous load: 48 W
  • Budget with reserve: 60 W
  • DC output current budget: 2.5 A

Assumptions & limits

  • Pload = PLC / other W + coil count × holding W + sensor count × sensor W.
  • Pbudget = Pload × (1 + reserve / 100); Ibudget = Pbudget / DC voltage.
  • Reserve is a planning assumption, not a manufacturer requirement.
  • All listed loads must match the selected DC voltage. AC coil VA and DC coil watts are not interchangeable.
  • Check coil pull-in peaks, simultaneous starting, temperature and altitude derating, overload behaviour and branch protection separately. This tool does not select a supply model.
  • Preliminary planning only. Final selection needs project-specific engineering verification.

Method reference: MEAN WELL — Power supply selection FAQ

Three-phase voltage unbalance — worked example

Example inputs

  • L1–L2 voltage: 415 V
  • L2–L3 voltage: 410 V
  • L3–L1 voltage: 420 V

Example result

  • Average line voltage: 415 V
  • Maximum deviation: 5 V
  • Voltage unbalance: 1.2 %

Assumptions & limits

  • Unbalance (%) = 100 × maximum absolute deviation from the average / average.
  • Use line-to-line readings taken under the same operating condition.
  • No pass/fail limit or trip delay is selected. Check equipment limits and investigate supply conditions with a qualified engineer.
  • This method uses voltage magnitudes only; it is not an IEC negative-sequence calculation.
  • Preliminary planning only. Final selection needs project-specific engineering verification.

Method reference: US DOE — Energy Management for Motor-Driven Systems

Bring these details.

  • Motor nameplate, voltage and full-load current
  • Driven machine, torque profile and starts per hour
  • Control voltage, interlocks and emergency-stop requirements
  • Cable length, environment and supply capacity
Send your project brief ↗

Connect your application to the right components.

Explore these related component families, compare exact manufacturer references and build a quotation request.

Open the E-Shop

LOVATO manufacturer family images; exact configurations vary by model.

Send a BOQ or parts list

Continue the specification

Application and selection guides