# Solar power & integration

> Explore energy and storage needs, then review how the system will connect to the site. Roof area and daily energy are only part of the specification.

Canonical: https://nairobipower.co.ke/solutions/solar/
Last updated: 2026-11-10

Explore energy and storage needs, then review how the system will connect to the site. Roof area and daily energy are only part of the specification.

## Start with your operating requirements.

Start with actual energy use and the time of day it occurs. Identify essential loads separately from loads that can be deferred or curtailed.

[Request an application review ↗](https://nairobipower.co.ke/contact/?product=Solar%20power%20%26%20integration)

## Explore the equipment options.

Use these families to frame the system, then confirm the exact model and compatibility with an engineer.

[### Solar AC Combiner Boards

Explore family ↗](https://nairobipower.co.ke/products/lv-distribution-switchgear/solar-ac-combiner-boards/)[### Continuous Power & UPS Systems

Explore family ↗](https://nairobipower.co.ke/products/continuous-power/)

### Technical details and selection tools

[Browse shop products](https://shop.nairobipower.co.ke/products?category=Circuit+Protection)[Explore equipment ↓](https://nairobipower.co.ke/solutions/solar/#equipment-options)[Open sizing tools ↓](https://nairobipower.co.ke/solutions/solar/#hub-tools)

## Plan the next decision.

01 / Understand the duty

### Start with the operating picture.

Start with actual energy use and the time of day it occurs. Identify essential loads separately from loads that can be deferred or curtailed.

02 / Check the interfaces

### Gather the evidence.

Record existing supply, roof or ground constraints and the intended interaction with batteries or a generator. A daily-energy estimate is only a starting point.

03 / Agree the output

### Define the review you need.

Ask for a site-specific design review covering equipment compatibility, protection, installation constraints and operating assumptions.

## Work through a sizing scenario.

Choose a tool, replace the example inputs with site values, then save a scenario before changing your assumptions. Compare the results and include them in your project brief.

Enable JavaScript for interactive estimates or [ask our engineering team](https://nairobipower.co.ke/contact/).

## Start with the application.

### Daytime self-consumption

Compare generation with the interval load profile and export constraints.

### Backup and storage

Separate critical loads, autonomy and surge requirements from whole-site demand.

### Safe integration

Coordinate AC/DC isolation, protection, earthing, roof structure and inverter interfaces.

### Does the estimate guarantee annual yield?

No. The tool uses entered sun hours and simplified losses. A site-specific yield model, shading assessment and equipment design are required.

[← Explore all application hubs](https://nairobipower.co.ke/solutions/)

## Specify the whole working system.

Start with the equipment duty. Add the control, protection and measurement functions that your project needs; these are options to review, not a pre-approved assembly.

### [Switch disconnectors](https://nairobipower.co.ke/products/control-components/families/disconnectors/)

Plan an appropriate isolation point for equipment and maintenance.

Confirm: AC or DC duty · pole arrangement · locking requirements.

[Compare selection details ↗](https://nairobipower.co.ke/products/control-components/families/disconnectors/)

### [Fuse holders and fuses](https://nairobipower.co.ke/products/control-components/families/fuses/)

Match the fuse system to the protected circuit and fault conditions.

Confirm: Fuse category · breaking capacity · replacement access.

[Compare selection details ↗](https://nairobipower.co.ke/products/control-components/families/fuses/)

### [Surge protection devices](https://nairobipower.co.ke/products/control-components/families/surge-protection/)

Coordinate surge protection with the earthing and supply arrangement.

Confirm: System voltage · SPD coordination · installation location.

[Compare selection details ↗](https://nairobipower.co.ke/products/control-components/families/surge-protection/)

### [Energy meters and power analyzers](https://nairobipower.co.ke/products/control-components/families/energy-meters/)

Measure demand and energy at useful points in the system.

Confirm: Measured circuits · accuracy needs · data integration.

[Compare selection details ↗](https://nairobipower.co.ke/products/control-components/families/energy-meters/)

### [Automatic transfer switch controllers](https://nairobipower.co.ke/products/control-components/families/transfer-controllers/)

Coordinate source monitoring and the transfer sequence.

Confirm: Source arrangement · interlocking · return-to-mains logic.

[Compare selection details ↗](https://nairobipower.co.ke/products/control-components/families/transfer-controllers/)

[Explore all 36 component families ↗](https://nairobipower.co.ke/products/control-components/)

### Continue into equipment & assemblies

[Solar AC Combiner Boards ↗](https://nairobipower.co.ke/products/lv-distribution-switchgear/solar-ac-combiner-boards/)[Continuous Power & UPS Systems ↗](https://nairobipower.co.ke/products/continuous-power/)

## Understand the estimate.

These examples use the default inputs. Change the live controls above for your own scenario; the reference examples below remain fixed.

### Solar PV sizing — worked example

### Example inputs

- Simultaneous peak AC load: 5 kW
- AC load power factor: 0.9
- Daily consumption: 12 kWh
- Peak sun hours: 5.5 h
- Panel wattage: 550 W
- Days of autonomy: 1
- Inverter: 1Φ (single phase)
- Storage chemistry: Lithium — 85 % usable

### Example result

- Array size: 2.8 kWp
- Panels required: 6
- Indicative inverter class: 8 kVA

### Assumptions & limits

- Hybrid inverter: 8 kVA, 1Φ single phase
- System losses assumed: 22 % (soiling, temperature, wiring)
- Peak sun hours: 5.5 h/day
- Inverter class considers entered simultaneous peak load and load power factor. Verify motor surge, overload duration, PV input limits and manufacturer ratings separately.
- Preliminary planning only. Final selection needs project-specific engineering verification.

### Cable sizing — worked example

### Example inputs

- Load current: 63 A
- Conductor material: Copper
- System phase: 3Φ (three phase)
- Derating factor: 1.00 — free air
- Installation method: Clipped direct / tray
- Cable type: SWA armoured
- Insulation: XLPE — 90 °C

### Example result

- Adjusted design current: 63 A
- Minimum conductor: 10 mm²
- Protective device: 63 A

### Assumptions & limits

- Insulation: XLPE, 90 °C conductor rating
- Conductor standard: BS EN 60228 class 2 stranded
- Installation method: clipped direct / tray
- Derating applied: 1.00 (combined factor 1)
- Confirm the selection against voltage drop and earth-fault loop impedance before ordering.
- Preliminary planning only. Final selection needs project-specific engineering verification.

### Water pumping duty — worked example

Hydraulic power (kW) = 9.81 × flow (m³/h) × total head (m) / 3600. Divide by pump and motor efficiency fractions for electrical input.

### Example inputs

- Water flow: 36 m³/h
- Total dynamic head: 50 m
- Pump efficiency: 70 %
- Motor efficiency: 90 %
- Daily operation: 8 h

### Example result

- Hydraulic power: 4.905 kW
- Electrical input: 7.786 kW
- Daily energy: 62.29 kWh

### Assumptions & limits

- Clean water density assumed 1000 kg/m³; gravity 9.81 m/s².
- Head must include static lift and pipe / fitting losses.
- Match pump curves and check NPSH, water quality and starting demand. No pump or motor size is selected.
- Preliminary planning only. Final selection needs project-specific engineering verification.

Technical reference: [KSB: pump power input](https://www.ksb.com/en-global/centrifugal-pump-lexicon/article/power-input-1117260). This reference does not certify the website calculation or an NPE assembly.

## Understand the estimate.

These examples use the default inputs. Change the live controls above for your own scenario; the reference examples below remain fixed.

### Managed EV charging capacity — worked example

### Example inputs

- Connected charge points: 8
- Maximum power per charge point: 7.4 kW
- Site active-power limit: 100 kW
- Other simultaneous site demand: 60 kW
- Configured EV power cap: 30 kW

### Example result

- Connected charging power: 59.2 kW
- Site headroom: 40 kW
- Managed EV allocation: 30 kW

### Assumptions & limits

- EV allocation = min(connected power, max(0, site limit − other demand), configured EV cap).
- All limits are active power in kW, not kVA. The equal-share illustration assumes every connected point requests power.
- This is a snapshot: building demand and vehicle acceptance change over time.
- Verify phase loading, minimum charging current, metering, controller communications and fail-safe behaviour. A low allocation may require queued or paused sessions; it does not guarantee every vehicle can charge.
- This does not size cables, protection, service capacity or certify charger compatibility.
- Preliminary planning only. Final selection needs project-specific engineering verification.

Method reference: [Schneider Electric — EV charging management systems](https://www.se.com/uk/en/product-subcategory/1840-ev-charging-management-systems/)

## Bring these details.

- Electricity bills and daytime / overnight load profile
- Critical loads and desired backup duration
- Roof or land dimensions, shading and structural information
- Supply diagram, existing generator and approval requirements

[Send your project brief ↗](https://nairobipower.co.ke/contact/?product=Solar%20power%20%26%20integration)

## Related equipment & services

[Solar & EV Charging Infrastructure ↗](https://nairobipower.co.ke/services/solar-ev-charging/)[Solar AC Combiner Boards ↗](https://nairobipower.co.ke/products/lv-distribution-switchgear/solar-ac-combiner-boards/)[Continuous Power & UPS Systems ↗](https://nairobipower.co.ke/products/continuous-power/)

## Connect your application to the right components.

Explore these related component families, compare exact manufacturer references and build a quotation request.

[Open the E-Shop](https://shop.nairobipower.co.ke/products?category=Circuit+Protection)

LOVATO manufacturer family images; exact configurations vary by model.

[Send a BOQ or parts list](https://shop.nairobipower.co.ke/bulk-order)

## Continue the specification

### Application and selection guides

- [Cable and protection selection](https://nairobipower.co.ke/products/cables-wiring/selection-guide/)

### Related engineering methods

- [Cable sizing](https://nairobipower.co.ke/tools/cable-sizing/)
- [Radial feeder fault current](https://nairobipower.co.ke/tools/feeder-fault-current/)